Monday 18 December 2017

Week ending 15/12/17

First line support calls resolved last week included setting up a new user, confirming issue with Jet report view for non Jet users [Nav 2013] and confirming initial Jet access error post install down to connection data [Nav 2013].
Some chargeable time this week! At last but just before holiday season. :(
Completed on site training for 2 days covering sale and purchase ledger. [Nav 2013]. Developments completed included bespoke report enhancements and a proposed payment report which lists documents paid as well as overall payment per vendor. [Nav 2013].
Of the 3 quotes outstanding awaiting approval, we have been asked to split one into 2 phases and send on as 2 documents. Also set up some jobs in 2 databases so client staff can set up and test SQL synch by company and specific modules. This will then free up the start of another mini project so our quote approval should follow. [Nav 2013r2]. For another client we are now agreeing a start date of early March next year for 1 project and June for another [Nav 2017]. All looking positive and if all come off we will be busy in 2018.

Plans for this week include starting permissions and role centre assignment [Nav 2013], running through proposed re implementation plan with client [Nav 2018], updating dataport for one more column of data [Nav 2009 Classic] and re-issuing document including quotes as requested by client after splitting project into 2 phases.  So busy week for the week before Xmas.

That's it for this week folks. No more blogs until 2018 so have a great Xmas and New Year!